Eco-friendly

Design and construction of biomass boiler feeding system without milling in Power Plant B

Our company with Remak S.A. and Energy Institute built modern installation enabling podanie approx. 400 000 tonnes of biomass to the three OP-650 boilers annually.
The contract included: complete installation for delivery and unloading of biomass in the form of pellets and briquettes, transport systems, storage tanks with a total capacity of 4400 m3,  installations for processing, storage and distribution of the dust to the burners. It is the first such big biomass feeding installation to the burners.  

The contract realized Department of Industry and Energy in Katowice. 

Date of signing the contract: 9 August 2010
Completion date: November 2011

  • Investor: ENERGA Elektrownie Ostrołęka S.A.
  • Contractor: Mostostal Warszawa SA/Remak SA/Instytut Energetyki
  • Contract value: PLN 44,05 mln
  • Implementation period: 2010-2011
  • Country: Poland
  • Voivodeship: mazovian