Modernisation, anti-filtration protection of the right embankment of the Wisłoka River in km 8 + 800 – 16 + 074 along with construction of embankment roads in the towns of Chrząstów and Złotniki in the Mielec Commune, in the town of Brzysta in the Gawłusz
Over 8 months ahead of schedule, the consortium of Mostostal Warszawa S.A. and Acciona Infraestructuras S.A. completed modernisation of the Wisłoka embankments.
Within the scope of the contract, the consortium performed:
- modernisation of embankments,
- sealing the ground,
- embankment roads,
- embankment ramps,
- Złotniki - Berdechów ditch,
- disassembly and construction of the embankment lock in km 13+874,
- disassembly and construction of the embankment lock in km 9+272,
- signs and also control and measurement devices,
- renovation of embankment lock outflows in km 14+759 and km 15+052.
Date of signing the agreement: 28.06.2010
End date of the contract: 31.03.2014
Date of signing the final report: 17.07.2013
- Investor: Podkarpackie Management Board of Melioration and Water Devices in Rzeszów
- Contractor: Mostostal Warszawa S.A. / Acciona Infraestructuras
- Contract value: PLN 21.95 million
- Period of implementation: 2010 - 2013
Selected projects
Faculty of Architecture and Faculty of Engineering Management of the Poznań University of Technology
Total surface:
19 931 m2
Contract value:
71 875 790,22 PLN gross
Completion date:
18 months