Eco-friendly

Modernization and development of existing wastewater treatment station in Zakroczym

The scope of the task included construction and installation work on the expansion of an excess sludge landfill, a pumping station and a PIX station as well as the supply and installation of drainage lines and a sludge hygienization installation. All the work was carried out on the operating facility. Ultimately, the sewage treatment plant will reach a capacity of 1,750 m3 of sewage per day.

  • Investor: Zakroczym Commune
  • Contractor: Mostostal Warszawa S.A.
  • Contract value: PLN 1.5 million
  • Implementation period: 2005 – 2005
Selected projects