Eco-friendly

Modernisation of Northern Pipeline in Wieliszew

This investment is part of a wider project called: "Water supply and wastewater treatment in Warsaw", which aims to improve the quality of the capital's water so that it meets the highest quality standards in the EU.

First, preparatory earthworks and road technology were performed.

The new facility, which stood on the premises of the Northern Pipeline in Wieliszew, is the first in Poland, where dissolved air flotation is employed for water treatment.

Final acceptance took place on June 28,  2010 and the grand opening of the building took place on July, 1.

Investor: Municipal Water and Sewage Company in Warsaw

Contractor: Mostostal Warszawa SA, Seen Technologies Ltd., Energotechnika Sp. zoo.

Contract value: PLN 105 mln

Implementation period: 2008-2010

Country: Poland

District: Masovian