The scheduled technical solutions for the modernisation of the power plant included the installation of new pipe turbo-sets in place of the existing ones and this was directly related to:

  • rebuilding the turbine chamber, suction pipe and outlet from the power plant;
  • construction of a structure under the repair closure hoist to the upper water and gratings cleaner;
  • replacement of electric furnishings (including the switchboard, transformers and the device in the machine hall, facilities of electric devices).
  • Investor: Jeleniogórskie Elektrownie Wodne Sp. z o.o.
  • Contractor: Mostostal Warszawa S.A. / Navimor-Invest Sp. z o.o.
  • Contract value: PLN 17.6 million
  • Implementation period: 2009-2011.