General
Facility of Washing Mashines Amica Wronki in Wronki
The works encompassed comprehensive facility contruction. The total production and service space is 35 000 m2.
Investor: Amica S.A.
Contractor: Mostostal Warszawa S.A.
Contract value: PLN 65,7 mln
Implementation period: 1999–2000
Country: Poland
Voivodeship: wielkopolskie
Selected projects
Faculty of Architecture and Faculty of Engineering Management of the Poznań University of Technology
Total surface:
19 931 m2
Contract value:
71 875 790,22 PLN gross
Completion date:
18 months