Reconstruction of channels and floors in the depot hall at Wrocław Główny railway station

Contract value: PLN 29,99 mln gross
Completion date: 20 months

17 June 2021 Mostostal Warszawa signed a contract worth nearly PLN 30 million with PKP Intercity for the reconstruction of the elements of the locomotive hall at the Wrocław Główny station.

The subject of the contract is the reconstruction of inspection channels and floors in the depot hall at a parking station in Wrocław. On the premises of the facility, current and emergency repairs as well as technical inspections of traction vehicles from the first to the fourth maintenance level are performed. The aim of the investment is to raise the standard of rolling stock maintenance and work ergonomics. After the reconstruction, the water management of the facility will also improve.

The main provisions of the contract:
Contract value: PLN 29.99 million gross.
Completion date: 20 months from the date of the contract.
Payment term: 30 days from the date of delivery to the Ordering Party of a correctly issued invoice.
The warranty period is 36 months.
Performance bond: 5% of the offer price (gross price) contributed in the form of an insurance guarantee.