The contract encompassed construction of sports hall of dimensions 35,58 m x 44,93 m with back-office facilities and auditorium as well as land use arrangements. Part of the building adapted for social use has two above-ground stories, is covered with gable roof and does not have basement. Sports hall has one storey. The construction of the building is made of reinforced concrete combined with ceramic filler. The roof is supported on steel lattice girders.


Total surface of the buildings and social facilities:  1878,99 m2
Total surface of roads and pavements:  1042,00 m

Date of signing the agreement: 21.05.2009
Implementation period: from May 2009 to September 2010

Investor: Gmina Tarnów Opolski

Contractor: Wrobis S.A.

Contract value: PLN 4,2 mln

Implementation period:  2009–2010

Country: Poland

Voivodeship: Lower Silesia