Forbes Porozumienie dla Bezpieczeństwa w Budownictwie
Production hall in Świdnica
General

Production hall in Świdnica

The agreement for the realization of the task was signed 15 November 2006. The design works lasted from 20 November 2006 up to the mid-January 2007. After its completion, the construction works started, which lasted 5 months.    

Investor: Krause - Zakład Pracy Chronionej Sp. z o.o.

Contractor: Wrobis S.A.

Contract value: PLN 17,08 mln

Implementation period: 2006–2007

Country: Poland

Voivodeship: Lower Silesia