General

Production hall in Świdnica

The agreement for the realization of the task was signed 15 November 2006. The design works lasted from 20 November 2006 up to the mid-January 2007. After its completion, the construction works started, which lasted 5 months.    

Investor: Krause - Zakład Pracy Chronionej Sp. z o.o.

Contractor: Wrobis S.A.

Contract value: PLN 17,08 mln

Implementation period: 2006–2007

Country: Poland

Voivodeship: Lower Silesia