General
Extension of the Fordon Sewage Treatment Plant in Bydgoszcz (part 2)
The agreement for implementation of the task was concluded on 24 September 2007.
The scope of work encompassed construction of an installation for thermal processing of sludge deriving from the Fordon and Kapuściska sewage treatment plants.
- Investor: Miejskie Wodociągi i Kanalizacja in Bydgoszcz
- Contractor: Mostostal Warszawa S.A. / Hansol EME Co., Ltd.
- Contract value: PLN 86.0 million
- Period of implementation: 2007 - 2010
Total area: 480 m2
Contract Value: 8 887 mln PLN net (10 931 010 mln PLN gross)
Deadline for completion: 1 September 2026

Contract Value: 314,6 mln PLN gross
Deadline for completion: June 30, 2028

Contract Value: 48,85 mln EUR net
Deadline for completion: 30.09.2026

Total area: 5,966 m2
Contract Value: PLN 95.35 million gross
Deadline for completion: Within 36 months from the date of signing the contract

Contract Value: PLN 61.87 million
Deadline for completion: up to 21 months

Contract Value: PLN 65,30 million net
Deadline for completion: until August 18, 2023

Kraków Airport