General
Construction of the Oncology Centre of J. Śniadecki Specialist Hospital in Nowy Sącz
Our taks in this contract included:
- new facilities: segments A, B and C;
- reconstructed facilities: segments D and E;
along with internal utility networks, reconstruction and construction of new elements of the technical and municipal infrastructure.
The newly built Oncology Centre houses an outpatient clinic, a chemotherapy ward, two wards ready to accept approx. 100 patients, a central sterilisation unit and an operating theatre.
The work was supervised by the Southern Region.
Date of agreement conclusion: 22nd of July 2010.
Date of contract completion: October 2012.
- Investor: J. Śniadecki Specialist Hospital in Nowy Sącz
- Contractor: Mostostal Warszawa S.A.
- Contract value: PLN 25.51 million
- Implementation period: 2010-2012
Selected projects
Faculty of Architecture and Faculty of Engineering Management of the Poznań University of Technology
Total surface:
19 931 m2
Contract value:
71 875 790,22 PLN gross
Completion date:
18 months