Reconstruction of the Wrocław Główny railway siding
Projects

Reconstruction of the Wrocław Główny railway siding

Contract Value: 4,3 mln PLN net
Deadline for completion: July 2026

On July 18, 2025, Mostostal Warszawa signed a contract for the execution of construction works involving the reconstruction of the track system and the construction of a 3 kV DC catenary network on the Wrocław Główny railway siding.

Scope of Work

The scope of the contract includes, among others:

  • Construction and reconstruction of tracks in the locomotive depot area, including:
    - construction of two new entry tracks to the Wrocław Główny locomotive depot on a new route,
    - reconstruction of the existing track No. 647 (used for refueling PKP Intercity locomotives),
  • Construction of a new 3 kV DC overhead contact line,
  • Modernization of technical infrastructure, including:
    - improving the reliability of equipment power supply,
    - upgrading the lighting of switch heads and marshalling/loading areas,
    - reducing the impact of snowfall on switch operation,
    - enhancing safety at railway crossings,
  • Implementation of modern technological solutions to improve the reliability and safety of the railway system.

This project is a significant element in the modernization of PKP Intercity's technical facilities in Wrocław and will contribute to the continued development of railway infrastructure in the region.

The investment is scheduled for completion within 12 months from the date of contract signing.

photo. MW