Photovoltaic power plant PV Janikowo
The project will be executed on a turnkey basis (excluding panel supply) and includes the implementation of construction, road, electrical, energy, and telecommunications infrastructure for PV Janikowo (near Inowrocław). As part of the task, expansion of the existing GPO is also planned.
The construction of a photovoltaic power plant for PV Janikowo is the first Polish hybrid project, which involves connecting two independent RES installations (Photovoltaic Farm and Wind Farm) to one power source. To achieve this, bifacial module technologies and trackers, i.e., movable structures following the sun, will be used.
The power plant will consist of 30,500 panels. The main part of the contract is planned to be completed by September 30, 2025.
Obtaining the final permit for use in the scope of the network operator and the final acceptance protocol (obtaining FON) is expected to be completed by September 30, 2026.