Infrastructure

S19 Nisko Południe-Podgórze

Contract value: PLN 272.5 million gross
Completion date: 34 months

On 14 November 2018, the consortium of Mostostal Warszawa and ACCIONA Construcción signed a contract for the design and construction of 11.5 km of the S19 expressway from "Nisko Południe" to the "Podgórze". The contract value is PLN 272.5 million gross.

The task of the consortium running the investment in the "design and build" system was to design the expressway, obtain a decision on the permission for road construction, construct a road with engineering facilities and associated infrastructure, develop as-built documentation and obtain a permit for use.

The scope of works included the construction of a dual expressway with emergency lanes and a reserve of outdoor space for the third lane, with cross roads and access roads enabling connection to the existing road network, including removal of collision with technical infrastructure, environmental protection devices.

As part of the project, there also are made engineering structures: 5 road viaducts, 6 passages for animals, 9 culverts with an ecological function.

Details of the contract
Contract Value: PLN 272.5 million gross
Completion date: 34 months - including the designing time, were winter periods are counted, while completion of works were winter periods are not included - from 15 December to 15 March
Payment date: 30 days from the date of receipt of the invoice
The warranty period: 10 years
Due performance security: a bank guarantee of 10% of contractual remuneration, PLN 27.3 million