Infrastructure
Reconstruction of National Road No. 2 on the section of the Biała Podlaska ring-road
The agreement for implementation of the task was signed on 19 May.
The entire work, both construction and engineering, lasted approx. 15 months.
Date of contract completion: 31 December 2009.
- Investor: General Directorate of National Roads and Motorways in Warsaw
- Contractor: Mostostal Warszawa S.A. / Acciona Infraestructuras S.A.
- Contract value: PLN 146.02 million
- Period of implementation: 2008 - 2009
Selected projects
Faculty of Architecture and Faculty of Engineering Management of the Poznań University of Technology
Total surface:
19 931 m2
Contract value:
71 875 790,22 PLN gross
Completion date:
18 months