Section of A4 motorway: Rzeszów Centralny - Rzeszów Wschód
The agreement for the realization of the task was signed 26th February 2010. na realizację zadania zawarto 26 lutego 2010.
The whole works, both construction and engineering, lasted 2,5 years.
At almost 7-kilometre-long section of motorway were constructed:
- 9 road and motorway flyovers
- 3 bus bridges, including motorway bridges: MA161 of 512 m over two rivers and national road no. 19
- more than 10 km of motorway fencing,
- 8 km of baffle assembly
- 9 wildlife crossings
- Investor: GDDKiA w Rzeszowie
- Contractor: Mostostal Warszawa S.A., Acciona Infraestructuras S.A.
- Contract value: PLN 439,0 mln
- Implementation period: 2010 - 2012
- Country: Poland
- Voivodship: subcarpathian
Selected projects
Faculty of Architecture and Faculty of Engineering Management of the Poznań University of Technology
Total surface:
19 931 m2
Contract value:
71 875 790,22 PLN gross
Completion date:
18 months