Infrastructure
DK73 Kielce-Brzeziny/Morawica
Contract value:
PLN 77.9 million gross
Completion date:
21 months
As part of the investment, we will be built a GP-class road with a length of 4.2 km on the trail of the existing road DK73 from Kielce to Brzeziny and Morawica. There will be four intersections with traffic lights, footbridge in Bilcza and access roads, as well as acoustic screens to improve the comfort of residents. There also will be rebuilt the necessary infrastructure.
Date fo the signing the contract: 26/07/2018
Consortium: Mostostal Warszawa SA (leader - 71%), Masfalt Sp. with o.o. (partner) and Drogomex Sp. z o.o. (partner)
Value of the contract: PLN 77.9 million gross
Deadline for implementation: 26/04/2012
Maximum warranty period: 10 years
Selected projects
Faculty of Architecture and Faculty of Engineering Management of the Poznań University of Technology
Total surface:
19 931 m2
Contract value:
71 875 790,22 PLN gross
Completion date:
18 months