Infrastructure

Expansion of National Road No. 8 to the parameters of an expressway on the section from the border of the Mazowiecki Province / Łódzkie Province - Radziejowice.

Mostostal Warszawa's works were divided into the following stages:

  • Stage I: Construction of a viaduct over National Road No. 8 at the intersection of Skierniewicka Street at 413+619.94 km
  • Stage II: Expansion of National Road No. 8 to the parameters of an expressway on the section from the border of the Mazowiecki Province - Radziejowice (without interchange) from 408+753 km to 418+400 km
  • Stage III: Construction of an interchange in Radziejowice on National Road No. 8 at 419+050 km
  • Stage IV: Construction of an interchange in Adamowice on National Road No. 8 at 409+588 km

Signing of the agreement: 1 September 2010

Completion of the agreement: 23 August 2013

  • Investor: GDDKiA Branch in Warsaw
  • Contractor: Mostostal Warszawa S.A. / Acciona Infrastructure S.A.
  • Contract value: PLN 190.86 million
  • Implementation period: 2010 – 2013