Acciona Mostostal Warszawa is part of the Acciona Capital Group.

Report No. 49_Conclusion of a Contract for the Construction of the AGH Faculty of Physics and Applied Computer Science Building

03 September 2019

The Management Board of Mostostal Warszawa S.A. ("Company") informs that on 3 September the Company concluded the agreement with the AGH University of Science and Technology in Krakow for the execution of the task entitled "Construction of the Faculty of Physics and Applied Computer Science building at the AGH in Krakow KC - zp. 272 - 400/19 ".

 

The main contract assumptions:

• Contract value: PLN 36.29 million gross.

• Implementation period: 19 months.

• Payment deadline: 21 days from the date of receipt of the invoice.

• The maximum warranty period is: 5 years.

• Performance bond: 4% of contract value - bank guarantee.

 

Legal basis:

Article 17 para. 1 MAR - confidential information