Acciona Mostostal Warszawa is part of the Acciona Capital Group.

Report No. 45_Conclusion of the Contract with TAURON Wytwarzanie S.A.

05 September 2018

The Management Board of Mostostal Warszawa S.A. ("Company") hereby, informs that on 5 September 2018, the Company signed a contract with TAURON Wytwarzanie S.A. ("Ordering Party") seated in Jaworzno, for the implementation of the task titled: "Block 10 thermal insulation with adjustment of the heat output system at TAURON Wytwarzanie S.A. Łagisza Branch Power Plant in Będzin".

 

Contract value: PLN 66.08 million gross.

Deadline: 15 months from the moment of signing the contract.

Payment deadline: within 30 days from the date of receipt of a proper invoice issued by the Company.

The warranty period is 24 months - Basic Period, and 60 months - Extended Period.

Due performance security: 10% of the contract value.

 

Legal basis:

 

Article 17 para. 1 of MAR Regulation.

The Management Board of Mostostal Warszawa S.A. ("Company") informs that on 5 September 2018, the Company signed a contract with TAURON Wytwarzanie S.A. ("Ordering Party") based in Jaworzno, for the implementation of the task entitled: "Block 10 thermal insulation of with adjustment of the heat output system at TAURON Wytwarzanie S.A. Łagisza Branch Power Plant in Będzin".

Contract value: PLN 66.08 million gross.

Deadline: 15 months from the moment of signing the contract.

Payment deadline: within 30 days from the date of receipt of a correct invoice issued by the Company.

The warranty period is 24 months - Basic Period, and 60 months - Extended Period.

Due performance security: 10% of the contract value.

 

Legal basis:

 

Article 17 para. 1 of MAR Regulation.