Report No. 43_Conclusion of a Contract for the Construction of a Standby Heat Source at Elektrociepłownia Stalowa Wola S.A.

28 August 2018

The Management Board of Mostostal Warszawa S.A. ("Company") informs that on August 28, 2018, the Company signed a contract with Elektrociepłownia Stalowa Wola S.A. for the implementation of the task titled: "Construction of a reserve heat source in Elektrociepłownia Stalowa Wola S.A." with reference number 1 / II / 2018 / DT.

 

Contract value: PLN 55 million gross.

 

Implementation deadline: 15 months.

 

Payment deadline: within 30 days from the date of delivery of invoices to the Ordering Party.

 

The warranty period is 24 months - Basic Period, and 60 months - Extended Period.

 

Due performance security for: 10% of the contract value.

 

Legal basis:

 

Article 17 para. 1 of MAR Regulation.

The Management Board of Mostostal Warszawa S.A. ("Company") informs that on August 28, 2018, the Company signed a contract with Elektrociepłownia Stalowa Wola S.A. for the implementation of the task titled: "Construction of a reserve heat source in Elektrociepłownia Stalowa Wola S.A." with reference number 1 / II / 2018 / DT.

 

Contract value: PLN 55 million gross.

 

Implementation deadline: 15 months.

 

Payment deadline: within 30 days from the date of delivery of invoices to the Ordering Party.

 

The warranty period is 24 months - Basic Period, and 60 months - Extended Period.

 

Due performance security for: 10% of the contract value.

 

Legal basis:

 

Article 17 para. 1 of MAR Regulation.