Report No. 20_The Completion of the Construction of No. 5 Power Unit at the Opole Power Plant

31 May 2019

The Management Board of Mostostal Warszawa S.A. ("Company") informs that on 31 May 2019, the Company received a certificate of completion for no. 5 power block at Opole Power Plant from PGE Górnictwo i Energetyka Konwencjonalna S.A. (subsidiary of PGE Polska Grupa Energetyczna S.A.).

The unit No. 5 was handed over for operations before the deadline covered by annex to the contract, ie before June 15, 2019 (report 52/2018).

The date of commissioning of unit no. 6 remains unchanged from previous estimates, ie 30 September 2019.

Mostostal Warszawa S.A. participates as a partner of a consortium of Polimex-Mostostal S.A. and Rafako S.A. ("General Contractor") as part of the construction of nos. 5 and 6 power units at the Opole Power Plant, implemented by the General Contractor and GE Power, which is the general designer and acts as the plenipotentiary leader of the consortium managing the contract implementation.

Legal basis:

Article 17 paragraph 1 MAR Regulation.