Report No. 12_Conclusion of the BaseCamp Student House in Katowice Construction Contract

20 February 2020

Management Board of Mostostal Warszawa S.A. ("Company") informs that on 20 February 2020 it concluded with ST Katowice Krasińskiego Sp. z o. o. ("Employer") with its registered office in Warsaw an agreement for the execution of the task entitled: "Construction of BASECAMP KATOWICE - Collective housing - student house with accompanying functions and public utility services, including sports, trade, catering with internal installations, development of the adjacent area, including road and pedestrian communication system with a fire road and parking spaces at Zygmunta Krasińskiego 29 street, the Bogucice - Zawodzie district, in Katowice on roads 92/6, 92/8 and 92/10, registered area: 246901_1.0002, Bogucice-Zawodzie district, registration: 246901_1 Katowice".

Contract value: PLN 110.91 million gross.

Completion date: 18 months and 27 days.

Payment term: 30 days from delivery of a correctly issued VAT invoice.

 

The warranty period is:

1. 10 years for the structure, facade tightness and roof tightness,

2. 5 years for all other works which do not form part of the Works listed in item 1 above,

3. not less than two 2 years for materials and equipment, according to the manufacturer's warranty.

Pledge:

1. 10 years for the structure, façade, external waterproofing, including the roof system, and the Contractor's Design,

2. 3 years for other works,

3. at least 2 years from signing the Facility Acceptance Protocol in relation to the Project, all materials and devices that are part of the Works will have a guarantee and manufacturer's warranty.

Performance bond: bank guarantee of 5% of the contractual remuneration, i.e. PLN 5.1 million net.