Report 30/2021 Conclusion of an Agreement for the Construction of a Gas Boiler at ZW Katowice
26 July 2021
The Mostostal Warszawa S.A. Management Board ("Company") informs that on 26 July 2021, the Company concluded with TAURON Ciepło sp. z o.o. a contract for the implementation of the task entitled: "Construction of a Gas Boiler with a Capacity of 140 MWt at ZW Katowice for the Needs of the Heat Market".
The main provisions of the contract:
- Contract value: PLN 109.47 million gross.
- Completion date: 20/12/2023
- Payment term: 30 days from the date of delivery to the Ordering Party of a correctly issued invoice.
- The maximum warranty period is 60 months,
- Performance bond: 10% of remuneration in the form of a bank guarantee.