Acciona Mostostal Warszawa is part of the Acciona Capital Group.

The new contract for Mostostal Warszawa. The company will build a science and laboratory building for AGH University of Science and Technology in Krakow

09 July 2018
Mostostal Warszawa will build new building for the AGH University of Science and Technology in Krakow.
 
The designed facility will be used by the Oil and Gas Drilling Department and the Faculty of Electrical Engineering, Automatics, Information Technology and Biomedical Engineering of the AGH University of Science and Technology. The building was designed as a building with five aboveground and one underground storeys, on the projection of an elongated rectangle.
 
At the cellar level will be locatted laboratories associated with the Oil and Gas Drilling Department, the upper storey will be divided between the departments of Oil and Gas Drilling Department and the Faculty of Electrical Engineering, Automatics, Information Technology and Biomedical Engineering.
 
Pavements around the building will be rebuilt, as well as existing parking and external stairs leading to the terrace of the academic canteen.
 
- This is another building that Mostostal Warszawa will build for the AGH University of Science and Technology. The construction of didactic and laboratory facilities for technical universities is always a challenge due to the specialized installations located in such facilities - says Janusz Stanaszek, Director of the Southern Division of Mostostal Warszawa.
 
The contract for the implementation of the investment was signed on June 28, 2018 in Krakow.
 
Construction: A science and laboratory building located on the eastern side of the existing S-1 building
Investor: AGH University of Science and Technology in Krakow
General Contractor: Mostostal Warszawa SA, Southern Division
The date of signing the contract: 28/06/2018
Deadline: 15/11/2019
Contract Director: Artur Sikora
Site manager: Mariusz Rudnik
Value of the contract: PLN 22 593 259.13 net