Acciona Mostostal Warszawa is part of the Acciona Capital Group.

S7 Załuski-Modlin Team Conducts Health and Safety Campaign for the Youngest

09 December 2024

To celebrate St. Nicholas Day, the S7 Załuski-Modlin team organized a special educational campaign for preschoolers from the kindergarten in Kroczewo, donating a fire evacuation kit. In addition to receiving valuable safety knowledge, the children were also given gifts, including coloring books and sweet surprises.

- Our goal is to promote and shape proper safety attitudes among the youngest. This is another educational initiative we have prepared for children from the vicinity of our investment project - said Tomasz Adamczyk, Construction Manager of S7 Załuski-Modlin.

1

Read about last year’s educational campaign by the S7 Załuski-Modlin Team

S7 Załuski-Modlin

The construction of S7 Załuski-Modlin is an infrastructure project worth PLN 635.06 million gross, in which Mostostal Warszawa is implementing:

  • 12 km of the S7 expressway with a dual carriageway and three traffic lanes,
  • Two road interchanges: Załuski and Ostrzykowizna,
  • A section of the new route of National Road No. 62 near the Ostrzykowizna interchange, parallel roads servicing adjacent areas, environmental protection devices, and road traffic safety infrastructure.

Mostostal Warszawa has already completed a significant part of the contractual tasks:

  • 90% of embankments,
  • 92% of auxiliary roadbeds,
  • 70% of bituminous works on the main route and side roads, amounting to over 260,000 tons of mineral-asphalt mixtures laid.

The works are expected to be completed in 2026.