Acciona Mostostal Warszawa is part of the Acciona Capital Group.

Mostostal Warszawa with a strategic contract for work on the construction of the Ostrołęka Power Plant

09 August 2019

On 9 August this year Mostostal Warszawa SA and GE Power Sp. z o.o. concluded a contract for the execution of construction works at the Ostrołęka C Power Plant. The contract value is PLN 609 million net.

The specified scope of works in the contract includes partial construction as part of the Main Building, construction of carburizing facilities, ancillary facilities, networks and roads.

- Mostostal Warszawa will have opportunity to confirm its unique expertise in the field of energy construction. After a number of efficiently implemented projects, including construction of blocks No. 5 and 6 in Opole, Ostrołęka C is another project from this segment that we will be implementing - says Miguel Angel Herras Llorente, President of the Management Board of Mostostal Warszawa.

The general contractor for the construction of unit C at the Ostrołęka Power Plant is the GE Power consortium with which the Ostrołęka Power Plant signed a contract in July 2018. The total cost of the investment is PLN 6 billion.

Details about the contract
Contract value: PLN 609 million net
Completion date: 33 months

Click to read more about the other Mostostal Warszawa projects in the energy construction sector