Mostostal Warszawa with a contract for S11 Zegrze Pomorskie-Kłanino

07 February 2020

7 February 2020 Mostostal Warszawa and General Director for National Roads and Motorways signed a contract for the execution of S11 expressway from Zegrze Pomorskie to Kłanino, with a lenght of 19,28 km. Gross contract value: PLN 478,30 million.

Section will start in the Zegrze Pomorskie node, which will be executed under the Koszalin-Zegrze Pomorskie section. Course largely runs through the woodland. Road runs at south of the Zegrze Pomorskie airport, then north of Krępa and Dragiń. At south of Kłanino course will approach the current country road no 11. There is located a road node, which ends this section. In the region of Dargiń constructor plans the rest area (MOP cat. I). S11 on this passage runs entirely along the new course.

- After succesful infrastructure investments, e.g. official opening of the Strzyżów bypass on January 31, we have acquired another crucial contract in the road construcion area. S11 expresway section, is an essential project for Mostostal Warszawa S.A. It strengthens our position as one of the key contractors in National Roads Construction Programme and increases our commitment in the West Pomeranian Voivodeship, for which we are executing other important investments – says Sławomir Barczak, Director of Infrastructure Area in Mostostal Warszawa S.A.

First S11 section in progress

S11 expressway connects directly Central Pomerania with Silesia through Wielkopolska. Until now, mainly the bypasses were implemented. Last year the Szczecinek Bypass was opened, the Olesno and Kępno Bypasses are under the construction. The Zegrze Pomorskie-Kłanino section is the first route fragment of the S11 expressway that enters the implementation stage.

Contract parameters:
Gross contract value: PLN 478,30 million.
Deadline for implementation: 36 months; winter periods (from December 15 to March 15) is not included in the realization time, project periods includes winter periods (from December 15 to March 15).
Payment term: 30 days from the date of receipt of the invoice.
Maximum warranty period: 10 years.
Performance bond: 10% of the gross contract value in the form of a bank guarantee.