On 20 May this year Mostostal Warszawa signed a contract with the General Directorate for National Roads and Motorways for the design and construction of the Praszka bypass along the national road No. DK45. The contract value is PLN 171.5 million.

The new route will be in considerable distance from built-up areas, thus it will ensure the ease of transit traffic, creating a combination of a supra-regional transit route connecting the Wielkopolskie, Opolskie and Śląskie voivodships. The implementation of the investment will also enable improved transportation to the investment areas, affecting the development of economic activities in area located in the vicinity of the national road No. DK45 and the Opolskie Voivodeship.

- The bypass of Praszka is a very important investment for Mostostal Warszawa. Today's contract is a sign of our company's involvement in the road construction area and it is about the significance of this segment to our portfolio - says Jorge Calabuig Ferre, Vice President of the Management Board of Mostostal Warszawa. - We also maintain our involvement in the Opolskie Voivodeship, where we are involved with the construction of new power units in the Opole Power Plant.

Description of the investment

The planned bypass will be of the GP technical grade and, it will consist of a single carriageway with two lanes with a lifting capacity of 11.5 t per axle. As part of the investment, 10 bridges and four roundabouts will be built. Environmental protection and road safety devices will also be built and technical infrastructure will be reconstructed (water and sewage network, gas, electricity, telecommunications and drainage devices). The length of the bypass will be 12.8 km. The implementation of the investment is planned in the "design and build" formula.
The beginning of the route will be located at the foot of the existing national road DK42 / 45, and then it will bypass the city of Gorzów Śląski from the west, and the city of Praszka from the east and end with a connection to DK45 on the north side of Kowale.

Details about the contract

Contract Value : PLN 171.5 million gross
Date of implementation: 36 months
Maximum warranty period: 10 years