The Management Board of Mostostal Warszawa S.A. (“Company”) declares that the Company (Consortium Leader), together with the consortium partner (“Petitioners”), jointly represented by the attorney-at-law, filed a petition in the District Court in Warsaw against the State Treasury – the General Directorate of National Roads and Motorways (“Defendant”) for payment of the amount of PLN 20,613,642.13 along with due contractual interest. The Company petitions for the amount of PLN 20,592,928.59 along with contractual interest.

 

The petition refers to the Petitioners’ claims related to the performance of the Agreement for “Extension of the S7 road to the dual carriageway on the ring road section of Kielce, Kielce (DK 73 kirsch - Chęciny - Chęciny)”.